Received 30th May! Not long to go now. According to the HIA contract, site start must commence 21 days after
- the essential information from the Owner (eg. land title ownership, bank loan approval, etc)
- all necessary building permits and planning approvals
- payment of the deposit
My Building Coordinator tells me site cut is scheduled for 16th June although this is just verbally over the phone.
The only other interesting note for the building permit is that this CBC company will need to come and inspect at various stages of construction. Piers, Pre Slab, Slab Steel, Frame, Re Frame, Garage Frame, and Final.