Building Permit Received!


Received 30th May! Not long to go now. According to the HIA contract, site start must commence 21 days after

  • the essential information from the Owner (eg. land title ownership, bank loan approval, etc)
  • all necessary building permits and planning approvals
  • payment of the deposit
My Building Coordinator tells me site cut is scheduled for 16th June although this is just verbally over the phone. 

The only other interesting note for the building permit is that this CBC company will need to come and inspect at various stages of construction. Piers, Pre Slab, Slab Steel, Frame, Re Frame, Garage Frame, and Final. 


Comments

Post a Comment

Popular posts from this blog

Interior Paint - Wattyl Winter Mushroom

Painting is complete. We've gone for the grey finish to the walls. Here's how the Winter Mushroom looks. Originally we thought of doing white for the architraves and doors but got convinced by the colour consultant to use the same paint all round. Was a bit worried at first but it has come off nicely. 

Cedar Plank Palandri Carpets Laid

Carpets were laid just before Christmas except for the master bedroom which was getting its squeaks fixed .  We picked the Palandri Category 2 carpets in Cedar Plank colour. Nothing too fancy as Category 2 was the included freebie and we didn't want to pay the Porter Davis premium for upgrades. Figured when it's better to let the kids wear out this one and replace it in a few years time at a much cheaper cost per square metre. Here's a roll of carpet. The most excited I've ever been to see a roll of carpet :)

PCI Checklist

My Practical Completion Inspection is on in about 12 hours time! Here's a comprehensive checklist I've copied from the Homeone forums.