Since contract signing, these are the extra post contract variations that I've had to sign off on... Variation 15th May At the time of receiving this first variation I was pretty darn frustrated. Site start was meant to be in May and here we are middle of May and they've only just done the corrections to the contract. Remember, my original site start was in MARCH! The changes were: Corrected 200mm wide wireware 2 tier slide out drawer with blumsoft closer. I was originally quoted $635 but this revised it down to $383 ($231 for the drawer and $152 for the soft closer) Corrected drawings to show floorboards under shelving in store room Corrected plaster void from 100mm to 1000mm from floor level in master retreat Remove Hallway doors - saved $1500! Updated tiling price to base off revised floorplan - saved $1000 Upgrade to HX35i - Got charged $1210 for this one even though I had this in my original contract at $800ish. Not happy. Update heating zone 1 to grou...