Skip to main content

Piers Stage

Finally the diggers were in, much to the delight of my kids. 

Here's the Engineering drawing to where all holes are meant to be dug. You can see where they have filled to the right of the 'line of cut', there are more piers than anywhere else. Must be because the fill in more unstable. This must be what my Tender BC meant when he said it would cost more if I was to move the line of cut and raise the slab more. ie. more piers would be required. 
I have noted that one of the strip footings needs to be poured separately to the slab and not tied in. When I mentioned this to the slab supervisor, he said they normally pour together but separate it with a plastic membrane. I also noted that there was no separate strip footing inspection required on my building permit. When I rang the building surveyor company that issued the permit to ask about this, they were not too fussed with this footnote and didn't think a separate strip footing inspection was required. 

Here's the guys doing their thing with their brand spanking new digger

The holes are meant to be a minimum 2.5m deep. I measured this one at almost 3m. Good work guys!

Here's the next day shot of one of the holes near the garage. I assume they've put some steel in there for strength before pouring the concrete.



And.. here's my lovely new meter box

This pier stage took a total of five days from site start. All in all, a pretty good start. The only complaint has been how the neighbour's fence is falling down and the PD guys aren't really giving much attention to it. The propping up of the fence was actually done by my lovely neighbours. Also the sub contractors haven't been closing up the temp fences, which is a security concern since it's wide open to my neighbours backyard.  They've also left a bit of mess on the entry crossover and road. 


Comments

Popular posts from this blog

Interior Paint - Wattyl Winter Mushroom

Painting is complete. We've gone for the grey finish to the walls. Here's how the Winter Mushroom looks. Originally we thought of doing white for the architraves and doors but got convinced by the colour consultant to use the same paint all round. Was a bit worried at first but it has come off nicely. 

Austral Hawthorn Bricks

Here's some photos of our Hawthorn bricks. These were category 4 upgrade and costs ~$5k. The off white mortar was another $1k on top. We chose to have the rolled joints instead of a flush finish. I think the off white mortar together with the rolled joints make the bricks stand out better and have been well worth the money.

External Elevation Drawings

These are the elevation drawings on how our house will look like. Wish they did a 3D model but this will suffice. This is our version of the Chatsworth facade. Notice the archway has been straightened to be more contemporary looking. One of our windows needs to be obscured. We've selected SatinLite finish instead of Spotswood glazing. The top of the balcony should be brick too so I've asked them to update it as a Post Contract Variation (even though I've picked it up before contract signing).  There's our extra laundry window and extended alfresco at the back Alfresco spanning the width of the house. Extra roller door to the back of the garage so we can drive straight through.  There's the big 3.6m feature window.  The maximum height they could do was 1.5m which is why it looks so short. Slight fall to the block so our house is cut in a bit more than we like it but that's how it's going to be done. At least we've increased the he...